Transparency International Georgia has investigated municipal procurement tenders for kindergarten construction in the Kobuleti villages of Khala, Gvara, and Kveda-Kvirike, where, according to the watchdog, work dragged on for years while the allocated budgets were repeatedly and substantially increased.
“A total of 43 amendments were made to the contracts, and the exact same pattern emerged in all three cases: the company that originally won the contract receives a substantial advance payment and abandons the site halfway through; the mayor’s office then issues a new, higher-priced tender, which is won unopposed by firms linked to the ruling party, Georgian Dream,” the investigation states.
According to the report, work in the village of Gvara was completed three years behind schedule, running 1,008,814 lari over the initial budget. Build Management LLC initially received 149,487 lari but failed to finish construction. The mayor’s office then increased the estimated project cost to 2,065,000 lari, and Gza—a company owned by Georgian Dream MP and prominent party donor Giorgi Chkonia (now owned by his daughters)—won the uncompetitive tender with no price reduction. As TI noted, the municipality subsequently extended the company’s deadlines and provided additional funding.
In Kveda-Kvirike, the project’s completion date has been pushed to November 2026—a four-year delay. During this time, construction costs increased by another 887,287 lari. The report notes that Build Management LLC served as the initial contractor here as well, taking 271,458 lari before halting work. Following five failed attempts, Mshenebeli LLC, a Georgian Dream donor, won the sixth tender worth 1,949,889 lari on an uncontested basis. The contract was revised 16 times, driving costs up by 187,179 lari, with the company receiving an advance payment exceeding half a million lari.
In the village of Khala, Transparency reports that the project was commissioned nearly four years late, resulting in a budget overrun of 221,422 lari. The Nika partnership received an advance payment covering 85% of the contract value—1,160,566 lari—yet failed to deliver the work despite 17 contract revisions. Ultimately, the mayor’s office had to contract Bza LLC for an additional 418,401 lari to complete the remaining work after a competing bidder was disqualified.
“Due to poor planning, a lack of oversight, and inflated tenders awarded to favored insiders, Kobuleti Municipality deprived children of kindergartens for years, while the municipal budget lost hundreds of thousands of lari,” the watchdog concluded.